Foundations:
· Remove forms and finish concrete on balance of wall and piers on Column Row A
· Continued placing stone base for concrete slab in building 2 (North End – between new concrete wall and existing building slab). Placed vapor barrier and reinforcing for slab in this area.
· Formed, placed, and finished concrete slabs in buildings 9 & 10 (At lathes)
· Completed undercut and backfill in Area 1 east of plant in preparation for concrete paving, and began undercut in Area 2
Building:
· Completed installing insulation and roofing on west side of building 1, and began installing roofing on north hip roof on building 1
· Began installing decking on building 3 (East side of plant)
· Continued framing trim-out and detailing on buildings 3 & 5
· Began erecting structural steel on buildings 8 & 11
Fire Protection:
· Contractor continued installing sprinklers in roof of Building 1; Contractor is hanging sprinkler piping in north to south direction; piping is in place from columns 9-25
Electrical:
· Continued layout and construction of primary underground piping to transformers 1-13
Site & Utilities:
· Graded alternate parking lot area and installed stone
· Installed mesh on drainage ditch and seeded area adjacent to alternate parking lot
RTO Relocation:
· Removed existing ductwork from RTO
· Removed existing RTO foundation piers in preparation for
relocation of RTO
· Removed unsuitable soils in preparation for placement of new RTO foundations
· Began backfill of excavation site for new RTO foundations
Winston Plywood
· Continued removing old presses and related equipment
· Continued refurbishing existing veneer dryers
Progress photos are attached.
Call with any questions you may have regarding items above