·Placed concrete grade beam on east end of Building No. 4 ·Placed footing and grade beam on west end of Building No. 4 ·Placed slab on west side of Building No. 2 (Blocked out a section for installation of water line to the plant) ·Sawcut and demo’d concrete for Hog Room foundation
Building:
·Continued erecting structural steel framing on Buildings No. 8 and 11 ·Installed standing-seam roof sheets on north end of Building No. 1 ·Installed insulation and standing-seam roof sheets on Building No. 9 ·Began installing insulation and standing-seam roof sheets on Building No. 10
Fire Protection:
·Contractor continued installing sprinklers in roof of Building No.
1. Complete with exception of a few fittings and sprinkler heads in bay between columns 3-5 on south end of building. ·Began installing sprinklers in Buildings No. 9 & 10
Electrical:
·Continued layout and construction of primary underground piping to transformers 1-13. Underground conduits in place for Transformers No. 1, 2, 3, 5, 6, 7, 8, 9, 10, 11, 12, and 13. ·Formed, placed, and finished transfer pads for Transformers No. T5, T6, T7, and T10
Site & Utilities:
·Completed undercut and backfill in Area 1 east of building
·Undercut soils in Area 2 east of building in preparation for placement of soil-cement backfill ·Began undercut and backfill at site of new parking lot (south of and adjacent to existing parking lot)
RTO Relocation:
·Demo’d unsuitable soils for RTO foundation slab ·Installed forms and placed stone base for RTO foundation slab ·Placed reinforcing steel for placement of RTO foundation slab (Plan to place slab on Monday, 08-10-15) ·Demo’d existing concrete drive foundation and RTO control room slab in preparation for new fan drive motor foundation and
new RTO control room slab