Winston Plywood Weekly Update August 7
Foundations:
· Placed concrete grade beam on east end of Building No. 4
· Placed footing and grade beam on west end of Building No. 4
· Placed slab on west side of Building No. 2 (Blocked out a section for installation of water line to the plant)
· Sawcut and demo’d concrete for Hog Room foundation
Building:
· Continued erecting structural steel framing on Buildings No. 8 and 11
· Installed standing-seam roof sheets on north end of Building No. 1
· Installed insulation and standing-seam roof sheets on Building No. 9
· Began installing insulation and standing-seam roof sheets on Building No. 10
Fire Protection:
· Contractor continued installing sprinklers in roof of Building No.
1. Complete with exception of a few fittings and sprinkler heads in bay between columns 3-5 on south end of building.
· Began installing sprinklers in Buildings No. 9 & 10
Electrical:
· Continued layout and construction of primary underground piping to transformers 1-13. Underground conduits in place for Transformers No. 1, 2, 3, 5, 6, 7, 8, 9, 10, 11, 12, and 13.
· Formed, placed, and finished transfer pads for Transformers No. T5, T6, T7, and T10
Site & Utilities:
· Completed undercut and backfill in Area 1 east of building
· Undercut soils in Area 2 east of building in preparation for placement of soil-cement backfill
· Began undercut and backfill at site of new parking lot (south of and adjacent to existing parking lot)
RTO Relocation:
· Demo’d unsuitable soils for RTO foundation slab
· Installed forms and placed stone base for RTO foundation slab
· Placed reinforcing steel for placement of RTO foundation slab (Plan to place slab on Monday, 08-10-15)
· Demo’d existing concrete drive foundation and RTO control room slab in preparation for new fan drive motor foundation and
new RTO control room slab
Winston Plywood
· Continued refurbishing existing veneer dryers